Landmark Construction

Construction Site Map

Overview as of February, 2025

  • Structural steel decking is complete.

  • Roofing will begin this week.

  • Rough electrical is 90% complete.

Overview as of January, 2025

  • Masonry is complete.

  • Trusses are beginning to be installed.

  • Demolition in the school is beginning.

  • The roof will be completed by the end of January.

Overview as of December, 2024

  • Second story floor has been poured.

  • Masonry will be completed by the end of December.

  • Trusses will begin to be installed after masonry is completed.

Overview as of November, 2024

  • Structural steel is being installed.

  • Masonry is finishing up.

Overview as of October, 2024

  • Masonry has begun.

  • Air handler has arrived.

Overview as of September, 2024

  • Cement slab has been poured and completed.

  • Mason’s begin mid September.

Overview as of August, 2024

  • Footings are poured.

  • Slabs are beginning to be poured.

  • There is a new sidewalk from the school to the greenhouse.

  • The fences around the construction site will be modified to allow access to the greenhouse.

Overview as of July, 2024

  • Underground utilities have been installed.

  • Excavation is beginning.

  • Underground electrical is beginning.

Overview as of June, 2024

  • Sewer is going in.

  • Site work is progressing.

Overview as of May, 2024

  • First coordination meeting will be held next week.

  • Portables onsite will be moved this month.