Landmark Construction
Overview as of February, 2025
Structural steel decking is complete.
Roofing will begin this week.
Rough electrical is 90% complete.
Overview as of January, 2025
Masonry is complete.
Trusses are beginning to be installed.
Demolition in the school is beginning.
The roof will be completed by the end of January.
Overview as of December, 2024
Second story floor has been poured.
Masonry will be completed by the end of December.
Trusses will begin to be installed after masonry is completed.
Overview as of November, 2024
Structural steel is being installed.
Masonry is finishing up.
Overview as of October, 2024
Masonry has begun.
Air handler has arrived.
Overview as of September, 2024
Cement slab has been poured and completed.
Mason’s begin mid September.
Overview as of August, 2024
Footings are poured.
Slabs are beginning to be poured.
There is a new sidewalk from the school to the greenhouse.
The fences around the construction site will be modified to allow access to the greenhouse.
Overview as of July, 2024
Underground utilities have been installed.
Excavation is beginning.
Underground electrical is beginning.
Overview as of June, 2024
Sewer is going in.
Site work is progressing.
Overview as of May, 2024
First coordination meeting will be held next week.
Portables onsite will be moved this month.